https://www.engineeringnews.co.za
Construction|Consulting|Engineering|Flow|Installation|PROJECT|Safety|Storage|System|Water|Flow|Maintenance|Environmental|Infrastructure
Construction|Consulting|Engineering|Flow|Installation|PROJECT|Safety|Storage|System|Water|Flow|Maintenance|Environmental|Infrastructure
construction|consulting-company|engineering|flow-company|installation|project|safety|storage|system|water|flow-industry-term|maintenance|environmental|infrastructure

New spillway increases dam capacity

LONG WAY
The newly developed elongated spillway, aptly named the duckbill allows for 25% more capacity on the Garden Route Dam

LONG WAY The newly developed elongated spillway, aptly named the duckbill allows for 25% more capacity on the Garden Route Dam

3rd July 2020

     

Font size: - +

The installation of a newly developed spillway on the Garden Route dam in George, Western Cape, has successfully increased the potential capacity of the dam to 12.5-million cubic metres, says consulting engineering company Aurecon dam engineer Frank Denys.

The company was tasked to raise the Garden Route dam – the main supply for water-scarce George – in May last year and went about devising a novel solution for the dam owing to unique technical constraints.

The ‘duckbill’ spillway was developed, not only allowed for the dam’s existing storage capacity to be increased by 25%, but also to significantly increase the discharge capacity of the spillway so as to boost the dam’s safety by preventing overtopping.

“A duckbill spillway is a type of non-linear spillway, similar to the more generally-known labyrinth spillway,” explains Aurecon dam engineer Frank Denys.

He says the main aim was to increase the overflow length such that the spillway or weir can pass more flow for a given overflow depth. “This allows for construction of very long spillways, typically four to five times longer than a linear spillway, in a limited area.”

The existing Garden Route dam spillway was only 25 m wide. However, the non-linear spillway extended this distance to 80 m by curving the spillway in the upstream direction.

Raising the dam’s water level was originally envisioned to be limited to increasing the overflow sill of the spillway or installing some form of fusegate system on the spillway.

These options were subjected to technical feasibility studies and an environmental impact assessment. The various spillway gate options appeared attractive from a cost-perspective, but undesirable when considering long-term maintenance.

Further, reevaluation of the dam’s flood hydrology, following large flood events experienced in the recent past, resulted in flood peaks significantly higher than the original dam and the proposed gate options were designed for.

The updated hydrology required that the crest of the embankment also had to be raised to ensure its safety. A new spillway concept, with a significantly higher capacity than the previous alternatives, was devised to be able to pass the flood peaks with as low a head as possible to minimise how much the embankment would need to be raised by.

The main dam wall was raised 1.76 m by placing new earthfill on top of the existing embankment. This task had to be achieved in confined spaces, atop high slopes, mostly using available material of suitable quality from the dam basin, and some imported from commercial sources.

The construction period was seven months, from May 13 to December 12, last year. However, the various planning stages for the project date back over a decade, with the idea of raising the dam first being investigated as far back as 2004.

The main client and dam owner is the George local municipality, with project funding from the Regional Bulk Infrastructure Grant.

The 2.5 m raising of the full supply level of the dam equates to an increase in the storage capacity of 2.5-million cublic metres to a total gross storage capacity of 12.5-million cubic metres.

“This will add much-needed drought resilience to the water-supply system. Expanding an existing water-supply resource is also preferable to the development of new sites, as it limits the extent of the environmental impact to an already impacted site,” Denys concludes.

Edited by Zandile Mavuso
Creamer Media Senior Deputy Editor: Features

Comments

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.132 0.187s - 167pq - 2rq
Subscribe Now