Wind farms seek better, cheaper storage
Wind farm operators are under no illusion that their small power generation output will be inadequate to meet South Africa’s baseload issues. However, they believe that in time new storage measures and lower costs will change the game radically.
Aurora Wind Power head of construction Christiaan Swanepoel told media on a site visit to Wind Farm 1 that wind farms would need to generate 132 GW to supply Eskom’s current 44GW of baseload supply.
The reason wind needs to supply four times the demand is because each 2MW wind turbine only has a 30% to 40% average load factor, which is much lower than coal or nuclear energy.
Considering that the 47 turbines on this wind farm only deliver 90 MW into Eskom’s grid, it would take 22 000 wind turbines to replace all current power generation in the country.
The wind farm outside Vredenburg, 150 km north of Cape Town, was commercially activated on June 9 this year, which Swanepoel said was one month ahead of schedule and within budget.
“You would need three times the installed capacity to run baseload,” said Swanepoel. “And that’s only if the wind is not seasonal.”
That’s probably never going to happen any time soon, so what needs to be achieved is better, affordable storage technology, said Swanepoel.
“We need technology to store energy from wind and solar and must ensure it is cost effectively doable. Currently, concentrated solar power uses molten salt solutions to store power, but it costs a lot.”
Aurora has a 20-year build, own and operate contract with Eskom and won the bid in the second round of the Department of Energy’s Independent Power Producers Programme.
As renewable energy becomes ever more efficient and cost effective, the debate is heating up over the right energy mix for South Africa and other countries.
The push to increase renewable energy in the mix will be high on the agenda at next week’s International Renewable Energy Conference taking place in Cape Town.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation