Giyani water project subcontractor 'determined to fight to the end'

23rd January 2019

By: News24Wire

  

Font size: - +

Khato Civils, the subcontractors removed from the R3-billion Giyani water project, is preparing to fight tooth and nail for its reinstatement.

This follows the water and sanitation department's announcement on Tuesday that the contract between Lepelle Northern Water (LNW) and LTE Engineering had been terminated. LTE was meant to connect running water to 55 Giyani communities and sub-contracted Khato Civils for the job.

The contract was terminated two weeks after a 6-year-old boy fell to his death into a trench, which was allegedly left open by Khato Civils.

But Khato Civils is not taking the termination lying down.

CEO Mongezi Mnyani told News24 that the company was "determined to fight until the end". Lawyers were perusing the matter, he added.

Asked if he had been given a reason for the termination, he responded that LNW said Khato had not been "on the ground".

But Mnyani said non-payment from the government led to work being halted.

"We are currently owed for work done about R40-million, and we are entitled to be paid back what rightfully belongs to our company so that we, in turn, can pay the employees we had to retrench".

Mnyani added that the non-payment led to a situation in which his company owed suppliers and other sub-contractors. He said he did not understand why the contract had been terminated.

In a letter sent to LNW's CEO, PK Legodi on December 3, which News24 has seen, Mnyani urged Legodi to pay so that Khato could return to the site to complete the project.

The water and sanitation department paid LNW R44-million in October. But Mnyani says to date payment has not been forwarded to Khato Civils.

"To date, we have not received any explanation or been called to a meeting to discuss the matter", Mnyani said.

This was not the first time that Khato Civils stopped work at the project. In August 2017, the construction company halted operations after its sister company, South Zambezi Engineering, which was meant to supervise the development, was not paid R50-million.

Both companies are owned by businessperson Simbi Phiri.

The Special Investigations Unit (SIU) is currently in the process of recovering R2.2-billion related to the LTE-Lepelle tender, which is reported to have been awarded irregularly.

In October 2017, City Press reported that the department awarded the contract to LTE and its boss, Thulani Majola, is a close ally of Environment Minister Nomvula Mokonyane.

LTE, in turn, appointed Phiri's companies for the engineering and construction work. The department then piled more projects on to the contract, bringing the value of work awarded to LTE to more than R5-billion.

The initial project was meant to cost just over R500-million within a time frame of nine months. The budget over five years has since ballooned to R3.5-billion.

The water project is now subject to an investigation by Public Protector Busisiwe Mkhwebane, after reports that it was incomplete and that the water department failed to pay contractors until recently.

The department said that the decision was made by LNW and further queries should be directed to it.

Efforts to contact LNW spokesperson Simon Mpamonyane were unsuccessful.

Edited by News24Wire

Comments

Showroom

Stewarts & Lloyds
Stewarts & Lloyds

Stewarts & Lloyds today supplies steel and tube, pipe and fittings, valves, pumps, irrigation, fencing, profiling and roofing products. The cash...

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.065 0.116s - 152pq - 2rq
Subscribe Now